Change Window Duration
If the policy commit processes running in the change window exceed the allotted time, the processes that are currently in progress run to completion, and the policy commit processes that did not start are not performed. The policy commit processes will restart for all the selected devices during the next scheduled change window.
If the change window period is too short for all the processes to complete, we recommend that you edit the change window to do one of the following:
-
Increase the allotted time in the Settings
-
Split the original change window into several change windows, with fewer devices included in each change window